LWM KNG-Line 4
Industrie
2023
Cordeel Nederland BV
Kruiningen

LWM KNG-Line 4

Cordeel Nederland BV
LWM KNG-Line 4
Location
Kruiningen
Tonnage
1,350
Type
Industrie
Completion
2023
About this project

The project in detail.

‍1,350 tonnes of steel for a state-of-the-art production facility

Commissioned by Cordeel Nederland, Hutten Metaal Staalbouw handled the fabrication and assembly of more than 1,350 tonnes of steel for the expansion of Lamb Weston's production facility in Kruiningen.

Large-scale expansion of production capacity

With a production hall of approximately 20,000 m² and an integrated three-storey office, the new factory is a major expansion of the existing site.

The factory increases annual production capacity by no less than 195 million kilograms of potato products and is designed for an efficient, largely automated production process.

Steel construction on an industrial scale

A production facility of this size requires a robust and reliable steel structure. The combination of large-scale production processes, technical installations and different building functions places high demands on both design and execution.

By fabricating and assembling more than 1,350 tonnes of steel, Hutten Metaal Staalbouw made a key contribution to the realisation of this modern factory.

Built for the future

Sustainability and efficiency played an important role in the design. The factory was developed with a focus on energy-efficient production, water reuse and heat recovery.

A future-proof production site, supported by a solid steel structure.

Our scope

What we delivered

Project details

  • Project: Lamb Weston – KNG Line 4
  • Location: Kruiningen
  • Client: Cordeel Nederland B.V.
  • End user: Lamb Weston
  • Steel structures: more than 1,350 tonnes
  • Production hall: approx. 20,000 m²
  • Factory completion: 2024
  • Category: Industrial construction
Approach

From engineering to assembly on site.

Phase 01

Engineering

Tekla model and shop drawings developed together with the main contractor and the installer. Clash detection up front, so no surprises on the construction site.

Phase 02

Fabrication

Cutting, drilling, welding and blasting in our own hall. MIG/MAG welding throughout.

Phase 03

Surface protection

Blasting to SA 2½ and durable coating in line with corrosivity class C4. Resistant to harsh industrial conditions.

Phase 04

Assembly

Just-in-time delivery by low-loader. Assembly with mobile cranes and our own certified assembly team, VCA**.

“
By fabricating and assembling more than 1,350 tonnes of steel, Hutten Metaal Staalbouw made a key contribution to the realisation of this modern factory.