About this project

The project in detail.

1,800 tonnes of steel for the Feringa Building in Groningen

On the Zernike Campus in Groningen stands the Feringa Building: a remarkable university building where science, innovation and technology come together. Commissioned by Ballast Nedam, Hutten Metaal supplied approximately 1,800 tonnes of steel structures for this large-scale new-build project.

Impressive in scale and design

With a total planned floor area of approximately 64,000 m², a length of 260 metres and five storeys, the Feringa Building is one of the largest university laboratory buildings in the Netherlands.

The design by Ector Hoogstad Architecten consists of three interconnected V-shaped wings. Behind the distinctive façade are modern teaching spaces, offices and specialist laboratories for ground-breaking scientific research.

Steel construction for a technically challenging building

The combination of distinctive architecture, large-scale laboratory facilities and high structural requirements makes the Feringa Building a challenging construction project.

The building was designed with a focus on earthquake resistance, low-vibration research spaces and special load-bearing structures. An environment in which precision and structural reliability are essential.

With approximately 1,800 tonnes of steel structures, Hutten Metaal made a substantial contribution to the realisation of this remarkable building.

‍

Our scope

What we delivered

Project details

  • Project: Feringa Building – University of Groningen
  • Location: Groningen, Zernike Campus
  • Hutten Metaal's client: Ballast Nedam
  • Steel structures: approx. 1,800 tonnes
  • Execution by Hutten Metaal: 2020–2021
  • Total building area: approx. 64,000 m²
  • Category: Non-residential construction / Education & research

‍

Approach

From engineering to assembly on site.

Phase 01

Engineering

Tekla model and shop drawings developed together with the main contractor and the installer. Clash detection up front, so no surprises on the construction site.

Phase 02

Fabrication

Cutting, drilling, welding and blasting in our own hall. MIG/MAG welding throughout.

Phase 03

Surface protection

Blasting to SA 2½ and durable coating in line with corrosivity class C4. Resistant to harsh industrial conditions.

Phase 04

Assembly

Just-in-time delivery by low-loader. Assembly with mobile cranes and our own certified assembly team, VCA**.

“
For the Feringa Building of the University of Groningen, Hutten Metaal Staalbouw supplied approximately 1,800 tonnes of steel structures. Discover this remarkable steel construction project.