In just eighteen weeks, the complete steel frame of the new hyperscale data centre in Eemshaven was in place. That is 2,400 tonnes of steel, fabricated in our two production halls and delivered just in time.
The project was fabricated in two parallel phases. While hall 1 processed the columns and main girders for the first data hall, hall 2 was already working on the trusses for the second hall. This kept on-site erection running continuously, with no waiting time between phases.
A coating built to withstand the North Sea wind
Because of the coastal location, the entire structure has been given a C5-M class duplex coating. The steel was blasted to SA 2½. No snagging items at handover.
“The steel structure was up in exactly the planned week. For a project of this scale at this location, that is remarkable.”
With this completion, Hutten Metaal once again confirms its position as a trusted steel partner for data centres in North-West Europe. The team is now focusing on the next phase of the campus, which goes into production later this year.